top of page

Planet Pool

Turn-key Construction of Special Designed Fountain Pool

Planet Pool

Sakarya Serdivan is a “Time Park” themed park. Within this park area, there is a Planets Pool, a cinema building that shows 3D space displays and resting areas. The meaning and functionality of the Time Park is emphasized with the Planets Pool. The Planets Pool is designed with a diameter of 6 meters. The sun that stands still in the middle of the pool is 80 cm in diameter. The diameter of the planets varies between 30-40 cm. The other 8 planets around the sun rotate around the sun at different speeds. The rotation direction can be set clockwise or counterclockwise, and the rotation speed can be increased or decreased if desired.​

The water in the pool also rotates in a way that creates turbulence. The aim is to create a “Milky Way” effect with the color-changing mini lights located at the bottom of the pool.​

The Planets Pool is an engineering achievement with its design and rotation mechanism.​

Planets Pool, which is designed for public use "Time Park" called "Time" theme of the main part of the park. This pool is located on a total of 9 planet, 8 planets in the middle stands the sun rotates at different speeds around the planet. Clockwise direction of rotation as an option can be adjusted or reversed, if desired rotational speed increased or reduced.​

The water in the pool, but also to create the effect of the Milky Way rotates.

The floor of the pool in order to strengthen the impact of the Milky Way, each with different special effects, shimmering 44 x 1 W LED lighting is used.

9 pieces of stainless steel are placed around the base of the pool. This information contains detailed descriptions about each planet on the bases of the plaque placed.

DIMENSION: 6 m
PLANETS: Complete stainless steel
PLANET NUMBER: 9
FIXED PLANET: Sun
MOVING PLANETS: Mercury, Venus, Earth, Jupiter, Saturn, Neptune, Uranus
PLANET ROTATION SYSTEM: The complete stainless steel independent double-acting
ROTATION SPEED OF PLANETS: 2 d/d - 12 d/d
NUMBER OF LED LIGHTING, 44 pieces of stainless steel 1.3 W Power RGB LED
HARDWARE & AUTOMATION SYSTEMS: Disc filtering, automatic chemical dosing systems

Project Location

Sakarya, Türkiye

Project Owner

Serdivan Municipality

Project Start & Finish Date

Serdivan Municipality

Duration

48 Days

bottom of page