Demirkayalar Aquapark
Turn-key Half Olympic Swimming & Slide and Slide Fall Pool

Designed as an entertainment complex, this aquapark also includes a building for wedding organizations, a gas station and resting areas. There are adult slides in the aquapark section of the complex. The adult pool is one of the first prefabricated pools built with overflow in Türkiye.
Construction of 12 x 25 m measurement, 1.4 - 1.8 m depth 300 m² area and 520 m³ water volumed overflowing panel-liner pool
Construction of 3 x 6 m, 0.6 depth, 18 m² interior skimmer concrete-liner kid pool
Readymade locked panel with panel construction resistant to earthquake
Construction of readymade oval surfaced polyester overflow channel
Mosaic ornamented liner interior covering
Construction of 4x8 m measurement, 1.4 depth, 32 m² interior skimmer concrete-ceramic slide falling pool
Construction of 115 m³/h capacity sand filtration system (Filtration cycle Duration: net 5 hour/all pool water)
Construction of 13 m wide band rainbow slide
Construction of 120 m³/hour capacity water technique system for slide
Project Location
Kahramanmaraş, Türkiye
Project Owner
Demirkayalar Company
Project Start & Finish Date
01.06.2007 - 17.07.2007
Duration
47 Days